NPDES Permitting of CAFOs in Missouri
April 13, 2004
Missouri Department of Natural Resources
Water Protection Program
Water Pollution Control Branch
NPDES Permitting of CAFOs in Missouri
Contents
Introduction
Permit Applicability
Permit Process
Types of Permits
Construction Permit Applications
Operating Permit Applications
Permit Maintenance
Permit Transfer
Permit Renewal
Permit Termination
Tables
Table 1 Animal Thresholds
Table 2 Animal Units
Table 3 Fees
Table 4 Construction Permit Completeness Items
Table 5 Operating Permit Completeness Check
Introduction
The U.S. EPA has delegated authority to Missouri to issue National Pollutant Discharge Elimination System
(NPDES) permits under the Clean Water Act. In Missouri, the Clean Water Commission has the authority for this
program with the Missouri Department of Natural Resources Water Protection Program serving as the staff for the
Clean Water Commission. Missouri has established statutes, regulations and standards for entities to obtain
NPDES permits within that administrative system.
The following guidance is intended to assist an animal feeding operation in understanding the NPDES
permitting process in Missouri. While this guidance is helpful in applying for a permit, it does not contain
all of the information and details that may be necessary. Information contained within this document can
change. The producer is encouraged to contact the department early in the planning stage if specific questions
or unusual circumstance arise. In addition, the applicant should be familiar with the applicable laws and
regulations.
Permit Applicability
The first step in the permit process is determining if a permit is required. In order for an operation to be
required to obtain a NPDES permit, the animal feeding operation must be defined as a Concentrated Animal
Feeding Operation (CAFO). The following is the definition of a CAFO:
An operating location where animals have been, are, or will be stabled or confined and fed or maintained
for a total of forty-five (45) days or more in any twelve (12)-month period, and a ground cover of
vegetation is not sustained over at least fifty percent (50%) of the animal confinement area and meets one
(1) of the following criteria: A. Class I operation; or B. Class II operation that discharges through a
man-made conveyance or where pollutants are discharged directly into waters of the state which originate
outside of and pass over, or through the operation or otherwise come into direct contact with the animals
confined in the operation.
The class is a size category that is based upon the design
animal units or animal unit equivalents at an operation. The Class I category is further broken down
into subsets of Class IA, IB and IC. Operations that are smaller than the Class II category are unclassified.
Table 1 presents the classifications and animal number thresholds for each classification.
The animal unit is a unit of measurement to compare various animal types at a CAFO. One beef feeder is used
as the reference for comparison. The total animal units at each operating location are determined by adding the
animal units for each animal type. The animal unit equivalent is an equivalent animal type and weight that has
a similar amount of manure produced as one of the listed animal unit categories. Table 2 is a listing of various
animal units.
In addition to being defined as a CAFO, an operation may also be designated as a CAFO. The department may
designate an operation as a CAFO for reasons such as to correct noncompliance, when an unauthorized discharge
has occurred, or when a discharge results in a violation of water quality standards. Those designated
CAFOs must also obtain a NPDES permit.
Table 1 Animal Thresholds

Table 2 Animal Units

Permit Process
Types of Permits
There are two stages to the permit process. The applicant is first required to obtain a construction permit
prior to building or modifying an operation. After the construction is completed, the applicant must then
obtain an operating permit prior to utilizing the newly constructed operation. There are two types of operating
permits: a general permit and a site-specific permit.
CAFOs, with the exception of Class IA CAFOs, may apply for a general permit. The general permit for CAFOs is
valid for a five-year period. The permit requires the same effluent limits, operating conditions and monitoring
requirements for each operation. All facilities receiving a general permit must adhere to the conditions
contained therein until the date of expiration or until the facility obtains a site-specific permit. The
expiration date is the same for all general permit holders regardless of the date that they received the
permit.
CAFOs alternatively may apply for a site-specific permit. Certain operations, such as Class IA CAFOs or
those required to do so by the department, must apply for a site-specific permit. A site-specific permit is
typically valid for a five-year period.
A fee is required for each type of permit. These fees must be paid before a permit can be issued. Table 3
contains a list of the fees for each type of permit:
Table 3 Fees
Construction Permit $750.00
Construction Permit for Sewer Extension $300.00
General Permit $150.00
Site-Specific Permit $5,000.00 per year
Receiving a CAFO permit does not relieve an operation from obtaining other permits that may be required. For
example, an operation that will be undergoing construction that will disturb one acre or more of land is
required to obtain a land disturbance permit. A CAFO may also be required to comply with county or local
ordinances.
Construction Permit Applications
The construction permit application process begins with the operation concept. During the planning stages
of the operation and site selection, the applicant should be considering permit requirements and specific
water quality issues at the site. Some of the things that should be considered during the planning stages are
buffer distances, local geology and soils, available land application area, local climatic information, etc.
These items play a large role in the overall design and operation.
After a site concept and design has been selected, the producer will need to submit a construction permit
application to the department. The application should be submitted at least 180 days prior to the expected
beginning of construction. The construction permit application consists of a Form F and supporting documents.
The supporting documents need to contain enough detail to ensure that all environmental design requirements
are being met. Table 4 is a list of items that must be included in the application.
Table 4 Construction Permit Completeness Items
- Form F
a. Signature- Fee
- Neighbor Notice Proof of Notification
- Topography Map
- General Layout Drawing
- Nutrient Management Plan
- Engineering Report
a. P.E. Certification b. P.E. Stamp on Drawings c. Narrative Design Summary d. Design Calculations e. Construction Specifications f. Operation and Maintenance Plan- Geohydrologic Evaluation (for earthen basins)
- Soils Report
a. Construction Materials b. Land Application Sites
The department will conduct a completeness check of the
application. This check is meant to determine that the applicant has attempted to address the
required items listed above. In the event that the application is found to be incomplete, the
applicant will be notified of the deficiency and will be provided an opportunity to correct the
deficiency.
Once the application is complete, the review of the application
begins. During this review, the department checks compliance with applicable laws and
regulations, determines if appropriate design standards have been met and reviews the nutrient
management plan. Questions or comments that the department has on the application are directed
to the applicant or engineer for response. The department can proceed in preparing a construction
permit once all issues on the application have been resolved.
The process for issuing the construction permit depends upon which type of operating permit will be sought.
For a general operating permit, a response to any comments from the neighbor notice will be prepared along with
the construction permit if applicable. Those responses will be sent out when the construction permit is issued
or denied. For a site-specific permit, the operating permit must be public noticed for at least 30 days.
After the public notice period ends, the construction permit proceeds in the same manner as that for
the general permit.
A construction permit is normally issued for a period of one year. The applicant may apply for one extension
of the permit. To request an extension, the permittee should submit a request to the department. The request
must be submitted 30 days prior to the expiration of the permit and must show that there are no substantial
changes in the original project.
Operating Permit Applications
After completing the construction project, the operation must apply for the operating permit.
There are two types of operating permits; the general operating permit and the site-specific operating
permit, but the application procedure is the same for each one. The application should be submitted at least
30 days prior to the expected commencement of operations.
The application consists of another Form F, the application fee and supporting documents. At this time the
Form F must contain a certification by a professional engineer licensed in Missouri. The operating permit
application is checked for completion by the department prior to processing. An incomplete application will
need to be corrected. Table 5 is a list of items that shall be included in the application.
Table 5 Operating Permit Completeness Check
- Form F
a. Signature b. P.E. Certification
- Fee
- As Built Drawings
- Engineering Report for Deviations from Approved Plans
Once the department is satisfied with the content of the submitted application, the operating permit can be
issued. In the case of a site-specific permit, the operating permit has already been prepared and public
noticed. A site-specific permit will not require another public notice unless there were significant changes
during construction. The operating permit can then be issued to the applicant, and the applicant can begin to
utilize the newly constructed operations.
Permit Maintenance
Permit Transfer
If an operation changes ownership the permit must also be changed. The process for this depends upon the
type of operation. A site-specific permit is transferable. In this case, the applicant submits a Form F to
notify the department of the transfer. General permits and construction permits are not transferable. The new
owner will need to apply for a new permit for these types. In any case, the original permittee retains
responsibility for the operations until the time the new permit is issued.
Permit Renewal
All operating permits have an expiration date. The applicant is required to submit a renewal application at
least 180 days prior to the expiration of the permit. The permit renewal consists of a Form F application. The
Form F application must be accompanied by the application fee. If the applicant has submitted a timely
application, the permit continues in the event that the department fails to take action upon the renewal
application prior to the expiration date.
Permit Termination
In the event an operation closes, the permit must be terminated. Prior to terminating the permit, however,
the operations must close the waste structures. A permit is required until all waste, wastewater and sludges
have been removed. At that time, the applicant may submit a Form H notifying the department of the closure of
the operation.